Tunnel Excavation work of SJVN’s Naitwar Mori HEP Completed
SJVN, a CPSE under Ministry of Power has completed the Tunnel Excavation work of its Naitwar Mori Hydro Electric Project in Uttarakhand. Sh. Nand Lal Sharma, Chairman & Managing Director, SJVN triggered the last blast to mark the completion of heading excavation of 4.3-kilometer-long Head Race Tunnel of 60 MW Naitwar Mori Hydro Electric Project. The newly constructed Office Complex, Transit Camp and Township ‘Yamuna Parisar’ was also inaugurated at the project site.
Naitwar Mori HEP has the potential to generate 265.5 million units of electricity every year and the State of Uttarakhand will get 12% free Power as a Royalty.
Addressing the employees, Shri Nand Lal Sharma, said, “We are glad to inaugurate the office complex with all the amenities for the upcoming Naitwar Mori HEP of SJVN. The project would further accelerate the Government of India’s commitment of providing Round the Clock (RTC) Energy to our nation and will also lead to the achievement of the Shared vision of SJVN, for becoming a 25000 MW Company by 2040. Timely completion of the Project as well as the welfare of the employees are the hallmarks of SJVN’s commitment.”
He urged all the SJVN employees and representatives of the contractors to strictly follow safety protocols and Covid Appropriate Behaviors.
SJVN is constructing its own Transmission Line of about 37 kms for transmission of electricity generated from the Project which is targeted to be completed by April 2022.
Commissioning of the Project will benefit the Area and particularly Project Affected Families as they will be provided an amount equivalent to the cost of 100 units of electricity per month for 10 years. SJVN is also taking up various development works in the vicinity of the Project towards under Corporate Social Responsibility (CSR).
****